Etwatwa Housing Project Phase 1

for Gauteng DPT of Human Settlement

Etwatwa Housing Project Phase 1

  • Raft foundation
  • Superstructure -cement bricks
  • Timber roof trusses
  • Cement roof tiles
  • Gypsum ceiling
  • Electrical
  • Plaster and paint
  • Plumbing
  • Solar Geyser

 

Discover more of our projects here. For more information about our sister companies head here.

Date

6th Dec 2016

Category

All, Completed

Start Date

29 October 2015

End Date

21 March 2017

Contract Period

17 Months

2625

new houses