Temi Construction is making progress on the all new Light Industrial Hub in KwaMnyandu

KwaMnyandu Light Industrial Hub Progress

PROJECT UPDATE: SEPTEMBER 2019

 

The KZN #temiteam is making consistent progress at the KwaMnyandu Light Industrial Hub, where construction in Ulmazi Section D has begun on the new split-level trading stalls, as well as the double storey office units.

 

These have steel roofing on a concrete-framed brick structure, with roller shutters and aluminium shopfronts for this retail development.

 

The scope of works also includes an ablution block that will be integrated into the main building, concrete entrance features, boundary fencing around the development and external paving as well as parking.

 

CLIENT:
KwaMnyandu Light Industrial Hub for eThekwini Municipality

 

PROJECT:
Construction

 

SCOPE:

Construction of :

  • 22 SMME trading facilities
  • 2 storage facilities
  • 2 ablution blocks
  • 5 offices
  • 4 takeaway shops
  • Parking
  • Landscaping

 

CONTRACT PERIOD:
16 Months

 

ANTICIPATED COMPLETION DATE:
February 2020

 

#temiconstruction #wedeliver #retaildevelopment #constructionSA #blackownedconstruction Discover more of our projects here. For more information about our sister companies head here.

Date

17th Sep 2019

Category

All, Current Construction Projects

Download the plans for KwaMnyandu Light Industrial Hub Progress

No Comments

Post a Comment

Comment
Name
Email
Website

ten + eleven =